Survey, isolation, installation, labelling, handover.

01

Enquiry by Email

Send the postcode, photographs, number of units, whether gas or water is involved and any tenant access restrictions to hello@quartermeter.com.

02

Desktop Review

Drawings, photographs and tenancy schedules are reviewed for £95 + VAT, credited against installation if instructed within 30 days.

03

Site Survey

Survey within 25 miles of Reading is £180 + VAT. From 25 to 45 miles it is £260 + VAT. Farther visits are quoted.

04

Quotation

The quotation states meter type, access assumptions, isolation needs, labels, photographs and schedule content. A 40% deposit secures materials and diary time.

05

Installation

Most two-to-six meter water jobs take one working day. Mixed gas and water rooms normally take two to three days including labelling and commissioning sheets.

06

Commissioning Pack

The handover pack includes serial numbers, tenant allocation, photographs, label references and access notes for future readings.

Enquiry

Documents required
Postcode, number of units, photographs, gas or water note.
Typical duration
Reply within working hours when enough photographs are supplied.
Common delay
No image showing where the branch pipes actually split.

Desktop Review

Documents required
Drawings, tenancy schedule and any existing meter list.
Typical duration
One to two working days for small blocks.
Common delay
Plans showing flat numbers but not pipe routes.

Site Survey

Documents required
Plant-room keys, riser access and permission to inspect stop valves.
Typical duration
Usually one to two hours on site.
Common delay
Locked cupboards, no parking or tenants not told about access.

Quotation

Documents required
Confirmed scope, billing details and preferred installation window.
Typical duration
Issued after survey once meter positions are confirmed.
Common delay
Unresolved responsibility for isolation or out-of-hours tenant notice.

Installation

Documents required
Deposit paid, access confirmed, service isolation notice served.
Typical duration
Two-to-six water meters normally one day.
Common delay
Stop valves that do not hold or boxed-in pipework discovered on the day.

Commissioning Pack

Documents required
Final tenant allocation agreed by landlord or agent.
Typical duration
Issued after installation photographs and serial numbers are checked.
Common delay
Door numbers, tenancy names and actual branch labels not matching.

Access and isolation

Client responsibilities before the van arrives.

  • Landlord or managing agent arranges tenant notice for any service isolation.
  • Plant-room keys, riser cupboard keys and safe reading access must be available.
  • Stop valves and gas test points must be accessible, not guessed at through boxing.
  • Parking or loading space must be arranged where materials and tools cannot be left in public corridors.

Real durations, not best-case promises.

2 to 6 water meters

Normally one working day where isolation, access and straight pipe runs are suitable.

6 to 12 meters

Usually two days, with labelling and photographs checked before handover.

Mixed gas and water

Normally two to three days including isolation, labelling and commissioning sheets.

Larger estates

Phased by staircase, riser or tenancy group so readings remain understandable.

Work turned away

I close the diary from 24 December to the first working Monday in January. If a managing agent has a January handover, send the drawings before Christmas; I will not pretend a plant room can be surveyed from a Boxing Day voicemail. Martin